SpaceX lays out $74 billion in data center plans for Arizona and Texas
SpaceX plans a $50 billion, 6 GW supercomputer campus near Willcox, Arizona, and a $24 billion data center near Starbase, Texas. The Arizona plan faces a county zoning hearing on December 9 and organized local opposition.
Kiln, covering chips, data centers and power
, 3 min read
6 GWplanned power draw of the Arizona campus at full build-out
What to know
- SpaceX's plans total about $74 billion: about $50 billion for a campus in Cochise County, Arizona, and about $24 billion near Starbase, Texas, according to Bisnow.
- The Arizona campus would draw up to 6 GW in four phases of about 1.5 GW, backed by a 24 GWh battery system, according to Baxtel and Seoul Economic Daily.
- Cochise County's Planning and Zoning Commission holds a public hearing on the needed special use permit on December 9, Baxtel reported.
SpaceX has set out plans for two data center campuses worth about $74 billion combined: about $50 billion for a site in Cochise County, Arizona, and about $24 billion for 444 acres near its Starbase headquarters in South Texas. Bisnow reported the plans on November 13, citing an update SpaceX posted on its website on Thursday, November 12.
The company merged with Elon Musk's AI company xAI in February, and its AI computing has so far been concentrated around Memphis, Tennessee, where the Colossus sites face litigation from the NAACP and the Southern Environmental Law Center, according to Bisnow.
The Arizona campus
The Arizona project, called the Cochise Supercomputer Campus, covers 747 acres along U.S. Highway 191 near the Willcox Playa in the southeastern corner of the state, according to Baxtel. It was filed through an affiliate, Tombstone Resources LLC, as special use application SU26-22-191, because the land is zoned rural. KJZZ reported on November 10 that SpaceX was behind the filing; at the time the cost was not public.
The application describes up to nine buildings of about 493,000 square feet each, Baxtel reported. At full build-out the campus would draw up to 6 GW, added in four phases of about 1.5 GW. Seoul Economic Daily put that at about 33 times Arizona's largest existing data center, which uses 180 MW. Construction could start as early as March 2027 if the county approves the permit, according to Baxtel and Seoul Economic Daily.
Power and water
The campus would take power from the grid through local electric cooperatives rather than building its own power plant, according to Seoul Economic Daily and Baxtel. The plan pairs that with a 24 gigawatt-hour (GWh) battery storage system and 90 MW of gas-fired generators for backup only. The local co-op, Sulphur Springs Valley Electric Cooperative, peaks at about 250 MW, and it says the developer must pay for every grid upgrade the full 6 GW would need, Baxtel reported. SpaceX says it will spend about $3.6 billion on new transmission and substations and later hand them to the generation co-op AEPCO at no cost.
The buildings would be cooled with dry air systems that use no industrial water, according to both outlets. Baxtel reported a one-time fill of 3 million to 5 million gallons and 2 million to 3 million gallons a year for sanitation, with no new well in the Willcox basin. In Texas, by contrast, the data center would run on a natural gas plant that SpaceX would build, own and operate, Bisnow reported, citing Bloomberg.
Local opposition
A November 4 community meeting at Cochise Elementary School was packed, with protest signs and booing, according to Baxtel, and an online petition against the project had about 2,100 signatures by that week. Seoul Economic Daily later put the count at 2,400. Residents have pointed to the Willcox Playa, a stopover for sandhill cranes. The Planning and Zoning Commission's public hearing is set for December 9 in Bisbee, Baxtel reported.
SpaceX's figures include about 1,000 permanent jobs, $30 million to $100 million a year in property tax and up to $450 million in one-time sales tax, according to Baxtel. Seoul Economic Daily reported 5,500 construction jobs; Baxtel reported 3,000.
Why it matters
A 6 GW campus would be one of the largest data center plans in the country and would need a rural co-op that peaks at 250 MW to carry roughly 24 times its current load, so the December hearing is an early test of whether grid-plus-battery designs can win over communities that have pushed back on gas-fired sites. Kivorent has followed similar fights over the Kraft Group's Sutton, Massachusetts proposal, Minneapolis's new data center rules and Anthropic's purchase of gas generators from OnePWR.
Sources
- SpaceX Unveils $74B Data Center Plans In Texas, Arizona, Bisnow, November 13, 2026
- SpaceX Confirms 6GW AI Data Center Campus Plan for Cochise County, Baxtel, November 7, 2026
- SpaceX is behind proposed data center in Cochise County, KJZZ, November 10, 2026
- Musk Plans $50 Billion AI Supercomputing Campus in Arizona, Seoul Economic Daily, November 14, 2026
AI chips and data centersAI law and policy
Written by an AI correspondent under standards set by editor Jacob Knight. Spotted an error? Tell us and we will fix it.