Loudoun County halts new data center rezonings for up to a year
Loudoun County's supervisors voted 7-1 on November 17 to stop acting on data center and substation rezonings until new rules are done, home to the largest concentration of data centers in the U.S.
Kiln, covering chips, data centers and power
, 3 min read
33data center and substation applications now on hold
What to know
- Loudoun County's Board of Supervisors voted 7-1, with one abstention, on November 17 to pause legislative data center and substation applications.
- The pause runs retroactively from September 15 and can last up to one year, until new zoning and plan rules are adopted.
- Site plans and other administrative approvals still go ahead, and substations needed for grid reliability are exempt.
Loudoun County, Virginia, which has the largest concentration of data centers in the U.S. according to NBC4, has stopped acting on new data center rezonings. The county's Board of Supervisors voted 7-1 on Tuesday, November 17, to pause legislative applications for data centers and electric substations until it finishes rewriting its data center rules, according to Loudoun Now and Bisnow. Supervisor Umstattd (D-Leesburg) voted no and Supervisor Kershner (R-Catoctin) abstained.
The final vote follows a September 15 vote directing county staff to draft the resolution, which NBC4 and other outlets covered at the time.
What is paused
The pause covers legislative applications, meaning rezonings and special exceptions, for data centers and substations, Bisnow reported. It applies retroactively from September 15 and can run as late as September 2027. Administrative applications such as site plans and subdivision plans continue. The resolution lists 33 legislative applications now active, according to Bisnow.
Virginia law does not allow outright moratoriums, so the county relied on the 12-month window it has under state code to review a legislative application, Loudoun Now reported. County staff will keep accepting applications, which go into a backlog. Once the pause ends or new rules are adopted, the board will hear them, no more than five per meeting. An application nearing its 12-month deadline will be taken up if the applicant refuses to extend it.
Outlets described the length differently. Loudoun Now called it a 12-month pause and Bisnow said up to one year; FOX 5 reported 10 months, which is roughly the time left between now and September 2027. This story uses the retroactive September 15 start date that Loudoun Now and Bisnow reported.
Two exemptions apply. Substations judged necessary for grid reliability can still go to public hearing, and special tax districts such as the Route 28 district are excluded, Loudoun Now reported. Fifteen pipeline projects, totaling 10.5 million square feet, that were grandfathered under a March 2025 rule change can proceed separately, according to Bisnow.
Why the county acted
The board wants to finish Phase Two of its Data Center Standards and Locations work, which rewrites the zoning ordinance and comprehensive plan. Results of an impact study are expected next spring, Bisnow reported. Supervisor Briskman (D-Algonkian), who made the motion, said pending applications will be held until they can be reviewed under the new rules. Residents raised new substations and transmission lines during more than 90 minutes of public comment, including the Valley Link line across Short Hill Mountain, Loudoun Now reported.
Loudoun had about 53 million square feet of data centers in 2025, double the total five years earlier, according to Bisnow. NBC4 counted 233 data centers in the county in September.
Industry warns of lawsuits
County Attorney Leo Rogers told the board, "There's a real threat of litigation here," Loudoun Now reported. Nicole Riley of the Data Center Coalition said moratoriums signal that a place is closed for business, and land use lawyers argued the pause breaks Virginia law. The coalition told FOX 5 that data centers bring the county about $1.3 billion in tax revenue this year and 17,000 jobs, and said legal challenges are likely.
Other votes the same night
Loudoun was not the only local government to act on Tuesday. Hillsboro, Oregon, home to a large cluster of data centers west of Portland, extended its 120-day data center moratorium by six months while it studies code changes, KPTV reported. Michigan City, Indiana, passed a temporary moratorium on permits for future data centers that exempts a Google data center already under construction, WSBT reported. The ordinance requires two public workshops within 90 days.
These follow votes this week in St. Cloud and Rochester, Minnesota, and an earlier pause in Boise.
Why it matters
Loudoun has more data centers than any other U.S. county, so a pause there on new rezonings, even a temporary one, pushes developers toward land that is already zoned or toward other states, and it comes as Congress weighs making data centers pay their full grid costs. The fight over substations and transmission lines shows that the limit on growth is increasingly power delivery, not land. For background, see why data centers use so much power and water.
Sources
- Loudoun Supervisors Approve 12-Month Data Center Pause, Loudoun Now, November 17, 2026
- Loudoun Supervisors Halt New Data Center Approvals For Up To One Year, Bisnow via Yahoo News, November 18, 2026
- Loudoun County board approves 10-month pause on new data center applications, FOX 5 DC, November 18, 2026
- Loudoun County board pauses data center applications, NBC4 Washington, September 15, 2026
- Hillsboro City Council extends data center moratorium by 6 months, KPTV, November 18, 2026
- Data center moratorium passes in Michigan City, WSBT, November 18, 2026
AI chips and data centersAI law and policy
Written by an AI correspondent under standards set by editor Jacob Knight. Spotted an error? Tell us and we will fix it.