Utah county approves Valar Atomics' 3 GW data center and nuclear campus permit
Carbon County's planning commission approved a conditional use permit for Valar Atomics' Raceway Energy Campus near Price, Utah, without taking public comment. The plan starts with a gas plant and could add 40 to 120 reactors.
Kiln, covering chips, data centers and power
, 3 min read
3 GWplanned power for Valar's Raceway Energy Campus
What to know
- Carbon County's Planning Commission approved a conditional use permit for Valar Atomics' Raceway Energy Campus on November 12, with one vote against, according to The Salt Lake Tribune.
- The 640-acre campus on state trust land would use about 3 GW, first from a natural gas plant and eventually from 40 to 120 on-site reactors.
- The commission took no public comment; the county attorney said a public hearing was not required.
The Carbon County Planning Commission in eastern Utah on Thursday, November 12, approved a conditional use permit for Valar Atomics' Raceway Energy Campus, a data center and power project on 640 acres of state trust land near Price, according to The Salt Lake Tribune. Commissioner Lisa Simmons cast the only vote against. The Tribune did not report the full tally.
The commission did not take public comment on the application. County Attorney Christian Bryner told the roughly 200 people at the meeting that the commission was not required to hold a public hearing to approve the permit, the Tribune reported. Some attendees were removed by commissioners and sheriff's deputies after repeated outbursts.
What Valar plans
The campus would use about 3 gigawatts of electricity, according to the company, which the Tribune compared with about 4 GW for the whole state of Utah. Valar plans to start with a natural gas plant to power the data centers and eventually install 40 to 120 nuclear reactors on the site, cooled by helium in a closed loop. The data centers would use closed-loop cooling that is filled once and topped up, and Valar says it will use no local water, possibly trucking water in.
The application says low-level radioactive waste would be kept on site only until it is shipped to a licensed disposal facility, but it gives few details on storage, the Tribune reported. The paper did not report a cost for the project.
Utah's Trust Lands Administration approved Valar's lease of the 640 acres at its September 17 meeting, according to KSL, republished by East Idaho News. Canary Media reported the agency expects about $35 million in rent over 50 years. Valar runs a test reactor, Ward 250, at the Utah San Rafael Energy Lab in neighboring Emery County; the company says it reached criticality in June 2026.
Conditions and next steps
The permit requires an emergency response plan coordinated with the sheriff's office and fire marshal, workforce housing, community engagement, and plans to manage noise, water and waste, the Tribune reported. Valar still needs a county building permit and a traffic plan, an air quality permit from the Utah Division of Air Quality for the gas plant, and a construction permit from the U.S. Nuclear Regulatory Commission before it can build reactors.
Commissioner Kurt McFarlane raised concerns about East Coal Creek Road, the campus's first access route, saying, "It just won't hold up because of the trucks." Valar said it would pay for upgrades and later plans a new road on Bureau of Land Management land.
A bigger plan next door
Raceway is separate from Valar's larger Project Beehive, which seeks about 9,000 acres of adjacent federal land. NPR has reported that Beehive would include 456 small reactors and could produce 9.6 GW, according to KSL. Residents told the Tribune they have been given little information; one, MariAnne Lawrence, said their biggest concern is that they are not being told anything.
Why it matters
The approval clears the first local hurdle for a data center campus that would start on natural gas and bet on reactors that do not yet have federal construction permits, and it came without a public hearing at a time when other towns are slowing data centers down. Kivorent has covered the same pressures in SpaceX's $74 billion data center plans in Arizona and Texas, the Alaska lease for a gas-powered North Slope data center and Minneapolis's new data center rules.
Sources
- Carbon County approves permit for Valar Atomics' data center, nuclear project, The Salt Lake Tribune, November 13, 2026
- Nuclear-powered AI data center proposed on state and federal land in central eastern Utah, East Idaho News (KSL), October 1, 2026
- Nuclear-powered data centers? It's a tough sell in Utah coal country., Canary Media, October 14, 2026
- Castle Country, Valar Atomics
AI chips and data centersAI law and policy
Written by an AI correspondent under standards set by editor Jacob Knight. Spotted an error? Tell us and we will fix it.