Anthropic takes over $3.4 billion of gas generator orders to power its data centers

Anthropic agreed to take over about 1.7 gigawatts of Caterpillar natural gas generator orders from Texas supplier OnePWR Solutions for $3.4 billion, the Financial Times reported, giving it its own power for data centers.

Kiln, covering chips, data centers and power
, 2 min read

1.7 GWgas generation in the reported $3.4 billion deal

What to know

  • Anthropic took over generator commitments that San Antonio-based OnePWR Solutions had placed with Caterpillar, according to the Financial Times as cited by Fortune.
  • The deal also brings engineering and construction capabilities to install the equipment; Anthropic did not buy OnePWR itself, Analytics Insight reported.
  • Neither Anthropic nor OnePWR has commented on the deal.

Anthropic has agreed to pay $3.4 billion to take over orders for heavy-duty natural gas generators that a Texas equipment supplier had placed with Caterpillar, the Financial Times reported, according to Fortune. The generators add up to about 1.7 gigawatts of capacity and are expected to become available over the next two years.

The seller is OnePWR Solutions, based in San Antonio. Neither Anthropic nor OnePWR has confirmed the deal: Fortune said both did not respond to requests for comment, and Analytics Insight said both declined to comment.

What Anthropic bought

Anthropic did not buy OnePWR. It took over the generator commitments OnePWR had placed with Caterpillar about two years ago, along with engineering and construction capabilities to install the machines, according to Fortune and Analytics Insight. Analytics Insight, citing a person familiar with the matter, reported that Anthropic first planned to be a OnePWR customer before choosing to take over the orders, and that no OnePWR employees moved to Anthropic.

The deal had been visible in outline since late September. Investment bank Piper Sandler said in a memo then that it had advised OnePWR on the $3.4 billion sale of its power generation platform to an unnamed "frontier AI lab," Fortune reported. The FT report named the buyer.

Neither report says where the generators will be installed or how many units are involved.

Why a model maker is buying generators

Gas generators can be installed on site, so a data center can run without waiting years for a utility grid connection. Anthropic's IPO filing already flagged this. According to Fortune, the S-1 says some of its planned data centers rely on dedicated natural gas-fired generation and warns of rising competition for gas supply and pipeline capacity. The filing lists about $900.9 billion in total committed spending on computing and infrastructure (our story on the prospectus).

Anthropic has also signed large computing deals with cloud providers, including Lambda (our story). Owning generation equipment goes a step further, toward controlling its own power supply. Fortune called it the largest direct investment in power generation equipment by an AI company; Analytics Insight described it as the largest known single purchase of such equipment by an AI lab.

Part of a wider shift to gas

Data center builders are increasingly pairing campuses with their own gas plants. A venture of PPL and Blackstone agreed this month to build about 2 GW of gas, fuel cell and battery generation for a QTS campus in Pennsylvania (our story), and Alaska leased North Slope land for a gas-fired data center (our story). Google's Wyoming campus also makes its own power (our story).

Why it matters

Access to electricity is one of the main limits on how fast AI data centers can be built. By taking over 1.7 GW of generator orders already in Caterpillar's queue, Anthropic skips some of the wait for both grid connections and new equipment, and commits to burning gas at a time when local opposition to data center power use is growing (our story on Minneapolis).