PJM asks FERC for a 12-month grid study for data centers, first cycle ending in 2029

PJM Interconnection asked federal regulators on November 16 to study data centers and power plants together in a single 12-month cycle, but the first application window would not open until late 2027 and the first cycle would finish in 2029.

Kiln, covering chips, data centers and power
, 3 min read

12 monthsPJM's proposed study cycle for large loads

What to know

  • PJM filed its Fast Energization proposal with FERC on Nov. 16 in docket ER27-531, defining a large load as 50 MW or more at one site.
  • The first submission window would open in late November 2027, with a soft close in early May 2028 and the first cycle finishing in 2029, according to the filing.
  • The Data Center Coalition and the Corporate Energy Buyers Association warned PJM in October that the annual cycle could leave some projects waiting nearly two years.

The number in PJM's pitch is 12 months. The date that matters more is in the fine print: the first application window under the new process would open in late November 2027, close softly in early May 2028, and the first cycle would finish in 2029. A data center that starts looking for power in the mid-Atlantic today is looking at the old rules, or at a 2029 answer.

PJM Interconnection, the mid-Atlantic grid operator, filed what it calls Fast Energization with the Federal Energy Regulatory Commission on November 16, in docket ER27-531. It's PJM's answer to FERC's June order on co-located and large loads, and it would fold the study of new power plants and new large customers into one pass. Today a generator's interconnection clock runs about two years from application to agreement, according to a PJM slide from November 5 cited by Energy News Beat. Fast Energization swaps three system impact study phases for a screening phase of roughly four months and a single study.

Who counts as large

The filing defines a large load as 50 megawatts or more at one site. Fifty megawatts running around the clock is about 438,000 megawatt-hours a year (50 × 8,760 hours). The campuses we've covered in PJM territory are far bigger: TeraWulf's planned Muskie campus in Kentucky is meant to reach 1 gigawatt, twenty times the threshold, and Ohio regulators just approved 2,150 MW of off-grid gas plants for two data center sites.

Getting in won't be cheap. Applicants would post full readiness deposits up front and sign cost recovery agreements with a minimum 10-year term, committing to 80% to 100% of a benchmark revenue figure backed by full credit support, POWER reported. PJM would also limit how much on-site generation a retail customer can net against its load to a 50 MW daily reduction starting March 16, 2027. A separate filing, ER27-522, sets ride-through rules for computing loads of 50 MW or more from January 16, 2027, so a data center doesn't drop off the grid during a voltage dip.

PJM asked FERC to rule within 120 days, which puts a decision around mid-March 2027.

The two-year worry

The data center industry wanted speed and isn't sure this is it. In an October 2 letter to PJM's board, the Data Center Coalition and the Corporate Energy Buyers Association argued that an annual cycle could have the opposite effect. Their reasoning, as Energy News Beat summarized it: a project must clear a utility's own study before it can join PJM's queue, so one approved just after a cutoff could wait almost a year for the next window and then another year inside it. They pointed to FERC's expectation of studies in 60 to 90 days.

That's the real tension. Twelve months is fast for a power plant. For a data center developer paying for land and chips, it's a year on top of the utility's own study. PJM has its own counterpoint: only about 5% of applications arrive correct and complete on the first try, according to The Duck Curve's summary of the filing, which suggests some of the delay sits with applicants.

How the other grids priced it

PJM wasn't alone. Six grid operators answered FERC between November 13 and 20, and several put a price on when a data center that takes cheaper, interruptible service gets cut off. POWER's tally: SPP caps bids at $25 per megawatt-hour, MISO uses a $100/MWh threshold, NYISO a $200/MWh maximum bid and ISO-NE a $250/MWh re-dispatch price. That's a tenfold spread in what it takes to switch off a server hall.

PJM is holding stakeholder sessions on November 23 and December 15, according to The Duck Curve. FERC hasn't set a comment schedule. For more on why these loads strain the grid, see our explainer on why data centers use so much power and water, and our coverage of the Senate permitting bill that makes data centers pay for the grid, Kentucky Power's gas plant for TeraWulf and Ohio's off-grid gas plants.