Senate passes permitting bill that makes data centers pay for the grid, 62-33

The Senate passed the Bipartisan American Affordability and Jobs Act 62-33 on November 19, sending the House a permitting overhaul that would make data centers pay their own transmission costs.

Kiln, covering chips, data centers and power
, 3 min read

$35BMore data centers would pay for transmission over 10 years

What to know

  • The Senate passed the Bipartisan American Affordability and Jobs Act 62-33 on Thursday, November 19, with 15 Democrats voting yes.
  • Sen. Martin Heinrich's office says data centers would put about $55 billion toward transmission over the next decade, about $35 billion more than under current policy, citing Grid Strategies.
  • The bill goes to the House, which passed a narrower permitting bill last year; amendments to ban data centers on public lands never got a vote.

Spread across ten years, the data center piece of the permitting bill the Senate passed Thursday night comes to about $3.5 billion a year. That's the extra amount data center owners would pay for transmission lines under the bill, compared with today's rules: roughly $55 billion over the decade instead of about $20 billion, according to figures from consulting firm Grid Strategies that Sen. Martin Heinrich's office released after the vote. The money doesn't disappear. Under current policy, much of it lands on everyone else's power bill.

The Bipartisan American Affordability and Jobs Act passed 62-33 on November 19, according to the Associated Press and a release from Sen. Cynthia Lummis's office. Fifteen Democrats voted yes, including Minority Leader Chuck Schumer, the AP reported. Republicans Josh Hawley of Missouri and Mike Rounds of South Dakota voted no, and so did Sen. Alex Padilla (D-Calif.), who told the AP he wrote many of the bill's transmission provisions.

That 62 is eight fewer yes votes than the 70 that cut off debate on the substitute version earlier in the week. A cloture vote is where senators who want a bill finished say so; the final roll call is where some of them stop short.

Mostly a permitting bill

Data centers are the part of this bill that reaches power bills, but most of its pages rewrite how the government says yes to things. Lummis's office lists firm deadlines for environmental reviews under the National Environmental Policy Act (NEPA), a 150-day limit on lawsuits challenging them, a narrower Clean Water Act Section 401 review for interstate transmission lines and gas pipelines, and a 150-day window to challenge an Endangered Species Act biological opinion. The AP said NEPA reviews now often take five years or more.

The four lead sponsors are the chairs and ranking Democrats of the Senate's energy and environment committees: Republicans Shelley Moore Capito of West Virginia and Mike Lee of Utah, Democrats Heinrich of New Mexico and Sheldon Whitehouse of Rhode Island. President Trump urged its passage on social media.

Heinrich's office also cites Rhodium Group estimates that the bill would cut electricity prices 3% to 5%, saving households $50 to $78 a year by 2040. Those are sponsor-chosen projections, and nobody outside the bill's backers has published a full score that we could read.

The amendments that never came up

The bill passed without amendments from rank-and-file senators, the AP reported. That shut out Oregon Democrats Jeff Merkley and Ron Wyden, whose proposals included a ban on building data centers on public lands. As local fights over siting multiply, from Loudoun County's application pause to San Francisco's moratorium, federal land is the one place this bill could have drawn a line and didn't.

The Sierra Club and the National Wildlife Federation opposed the bill. Jen Duggan of the Environmental Integrity Project called it "a gift to some of the biggest polluters in America," according to the AP.

The House clock

The bill now goes to the House, which passed a narrower, more industry-friendly permitting bill last year, the AP said. Capito and Sen. John Barrasso each urged House leaders to move quickly. They have reason to: as we reported Wednesday, a bill that isn't enacted before the new Congress opens in January has to start over, and House Democratic leader Hakeem Jeffries, in line to become speaker, has said this version falls short.

One question for data center developers is still open. The bill sets the national rule that they pay full freight for their grid connections, but how that applies to projects already in line for transmission would be up to the Federal Energy Regulatory Commission, which gets 90 days after enactment to say, according to a White & Case analysis of the substitute. For a sense of how much power sits behind those connections, see our explainer on why data centers use so much power and water.