Frey's data center veto stands as Minneapolis moratorium runs out
The Minneapolis City Council voted 7-5 on November 20 to override Mayor Jacob Frey's veto of its data center ordinance, two votes short of the nine needed. The city's six-month moratorium expires November 21.
Kiln, covering chips, data centers and power
, 3 min read
7-5override vote; nine of 13 votes were needed
What to know
- The Minneapolis City Council voted 7-5 on November 20 to override Mayor Jacob Frey's veto of its data center ordinance, short of the nine votes required.
- The city's six-month moratorium on new data center development expires Saturday, November 21, according to KSTP.
- Frey said the ordinance would amount to a de facto ban and said he would sign the framework city staff first proposed.
Minneapolis spent six months writing data center rules so it would have something in place the day its moratorium ran out. That day is Saturday, and the city has nothing.
The City Council voted 7-5 on Friday, November 20, to override Mayor Jacob Frey's veto of the data center ordinance it passed last week, according to KSTP and FOX 9. An override takes nine votes on the 13-member council. Council member Jamison Whiting, who voted for the ordinance on November 12, was absent, KSTP reported. Even with him in the room, the count tops out at eight, one short.
The six-month moratorium on new data center development expires Saturday, November 21, KSTP reported. "Right now as we stand, there is no regulation on data centers," council vice president Jamal Osman said, according to WCCO.
What Frey objected to
The ordinance we covered on November 12 passed 7-6. It limited new data centers to existing buildings in two downtown overlay districts, capped server space at 150,000 square feet with renewable power or 50,000 without, and required each new center to win council approval.
That last piece is what the mayor fought. MPR News reported that Frey's veto targeted a late amendment requiring case-by-case council approval of any new data center, which he called arbitrary rule making. FOX 9 described his objection as the changes to primary zoning and the overlay district required for each site, and reported that he said the result would be a de facto ban. In his veto letter, according to MPR News, Frey said he would sign the framework city staff first presented, which he called one of the strictest in the country. He also argued, per FOX 9, that the city needs a strong commercial tax base to pay for social programs.
So the fight isn't over whether to regulate. It's over who decides each project: the zoning code, or a fresh council vote every time.
The gap
What fills the vacuum is the old zoning code. Before the November 12 vote, MPR News reported that without new rules, data centers would fall back to the existing code, which allows them with a permit in 10 of the city's 15 zoning districts. That is a much wider map than two downtown overlay districts. Council member Jason Chavez warned that the rest of the city would be wide open, WCCO reported, and suggested passing an ordinance Friday by unanimous consent. WCCO said the council expected to take up data centers again Friday afternoon; none of the reports said whether that happened.
The slower path is set. MPR News reported that the next set of regulations goes to the planning commission for a public hearing on December 14, with a final council vote on December 17. That leaves close to four weeks with no data center rules on the books.
How much that window matters depends on whether anyone files. FOX 9 reported last week that eight data centers already run downtown and that Xcel Energy has seen interest in up to eight more. None of this week's reports named a pending application.
Why other cities are watching
Most local fights this month ended in a pause, not a rulebook: Rochester passed a one-year moratorium, St. Cloud moved toward one, and San Francisco extended its own to September 2027. Minneapolis tried to go straight to permanent rules on a deadline and missed it by a veto. The question for December 17 is whether the council can find nine votes for its version, or seven for one Frey will sign. For why these sites draw such scrutiny, see why data centers use so much power and water.
Sources
- Minneapolis council falls short in attempts to override Frey vetoes on data centers, police chief, KSTP, November 20, 2026
- Minneapolis City Council fails to overturn mayor vetoes on police chief nomination, data center rules, FOX 9, November 20, 2026
- Minneapolis City Council fails to override Mayor Frey's vetoes on next police chief, data centers, WCCO / CBS Minnesota, November 20, 2026
- Minneapolis will try again to pass data center regulations next month, MPR News, November 20, 2026
AI chips and data centersAI law and policy