Kivorent News

Monday, November 23, 2026

Tech and AINews

Appeals court clears Amazon's $6 billion Shreveport data center despite NDAs

Louisiana's Second Circuit Court of Appeal on November 18 upheld Shreveport's special use permit for a STACK Infrastructure data center built for Amazon Web Services off Greenwood Road, rejecting residents' argument that city officials' nondisclosure agreements tainted the vote.

Kiln, covering chips, data centers and power
, 3 min read

$18BSTACK's three northwest Louisiana sites, about $6B each

What to know

  • A three-judge panel of the Louisiana Second Circuit Court of Appeal affirmed the dismissal of a suit against Shreveport's permit for the Resilient Technology Park data center on November 18.
  • The court said the nondisclosure agreements signed by city officials did not on their own justify reversing the City Council's approval, according to the Shreveport-Bossier Advocate.
  • STACK says it is under construction on all three of its northwest Louisiana sites, each about $6 billion, with first buildings online in mid-to-late 2027.

The strongest argument against Shreveport's Amazon data center was never about noise or water. It was that the people voting on it had signed nondisclosure agreements, and the residents suing said what those officials knew, and could not say, shaped the decision. On November 18, a Louisiana appeals court said that was not enough to undo it.

A panel of the Second Circuit Court of Appeal, Judges Stone, Stephens and Robinson, affirmed a Caddo Parish judge's April dismissal of the suit, the Shreveport-Bossier Advocate reported. The court took the petitioners' claims one at a time and found the NDAs alone did not "warrant a reversal" of the City Council's special use permit. Judge Stephens's opinion said council members had been briefed on all 12 zoning criteria in the city's development code and had a record that included dozens of public comments, so the court deferred to the city, according to 710 KEEL.

How it got to court

The site is Resilient Technology Park on Greenwood Road in west Shreveport, being developed by STACK Infrastructure for Amazon Web Services. KSLA and KEEL describe seven buildings. The city's planning commission did not approve the permit in December 2025; KSLA and KEEL call the vote a tie, which counts as a denial, while the Advocate gives it as 4-3 against. The applicant appealed, and on December 18 the City Council reversed the commission unanimously. Three petitioners, among them Mooringsport Mayor Tyler Gordon, sued.

Can they go further? KEEL says the petitioners could still ask the Louisiana Supreme Court to take the case, and BIZ Magazine says further review may be sought. None of the reports says whether they will. The Advocate calls this the final appeal. Either way, the permit stands today and the project is no longer held up in court.

The money and the jobs, side by side

STACK is building three campuses in northwest Louisiana for AWS: this one, one on Stateline Road near Blanchard in Caddo Parish and one on Highway 3 near Benton in Bossier Parish. Each costs roughly $6 billion to build and fit out, the Advocate reported, for about $18 billion in all. STACK's Josh Fenn told the Advocate the company is under construction on all three, with first buildings online in mid-to-late 2027 and the full campuses around 2029. KEEL puts the Shreveport build through much of 2028.

STACK told the Advocate the Resilient site will have about 210 permanent jobs. That works out to about $28.6 million of investment per permanent job ($6 billion divided by 210). Across all three sites, the Advocate says permanent employment rises to about 750, or roughly $24 million per job ($18 billion divided by 750). Amazon told KSLA its projects in the region will support up to 750 full-time data center jobs and about 2,500 other positions in the community.

That ratio is normal for the business. A data center is mostly chips, power gear and concrete, not payroll, which is why towns increasingly weigh the tax base and the grid load rather than the headcount. None of the reports gives the site's power draw in megawatts or its water use, the two numbers neighbors usually want most. We explain why those run so high in our explainer.

Secrecy keeps landing in court

Nondisclosure agreements are standard in data center site hunts, and they keep turning into legal arguments. In Georgia, residents sued OpenAI and Effingham County officials under the state's racketeering law over how Project Camellia was approved. Shreveport is the clearest answer yet from an appeals court: signing an NDA does not by itself void a zoning vote, as long as the public record shows the council weighed the criteria.

Amazon's footprint in the region keeps growing through partners. Earlier this month Blackstone's BXDC bought a 75% stake in 13 AWS data center buildings, and Louisiana's other giant project, Meta's Hyperion campus, has seen the cost of its Entergy gas plant rise 63%. The question for Shreveport now is the one the court never had to answer: how many megawatts the three STACK campuses will pull, and from whom.

Sources

AI chips and data centersAmazonAI law and policy

Written by an AI correspondent under standards set by editor Jacob Knight. Spotted an error? Tell us and we will fix it.