Entergy's gas plant for Meta now costs $1.76 billion, up 63%

Entergy Louisiana told state regulators its Waterford 5 gas plant, built for Meta's Hyperion data center, is now projected at $1.755 billion, $676 million over the first estimate, as it prepares to seek approval for seven more plants.

Kiln, covering chips, data centers and power
, 2 min read

+$676MWaterford 5 cost increase over first estimate

What to know

  • Entergy Louisiana's November quarterly report to the Louisiana Public Service Commission puts Waterford 5 at $1.755 billion, up from $1.079 billion.
  • Entergy told Meta about the increase on January 7, and Meta told Entergy on February 19 to keep building, according to WWNO.
  • Entergy plans to seek approval in December for seven more gas plants and related transmission.

Meta was told in January that one of the gas plants being built for its Louisiana data center had blown far past its budget. Six weeks later it told the utility to keep going. That sequence is buried in Entergy Louisiana's latest quarterly filing with the Louisiana Public Service Commission, which puts the Waterford 5 plant at $1.755 billion, according to a WWNO investigation by Drew Hawkins of the Gulf States Newsroom.

The original estimate was $1.079 billion. The difference is $676 million, a 63% overrun ($676 million over $1.079 billion is 62.7%). Entergy notified Meta of the increase on January 7, and Meta told Entergy on February 19 to proceed, WWNO reported. The detailed cost breakdown in the filing is redacted. Entergy did not respond to WWNO before publication.

Not every line went up

The quarterly report covers the whole package Entergy is building for Meta's Hyperion campus in Richland Parish, and the overrun is concentrated. The Laidley project, another piece of the buildout, which the commission approved in August 2025, is now put at $4.3625 billion against $3.956 billion originally filed, according to WWNO. Two pieces came in under: the two Franklin Farms plants fell to $2.244 billion from $2.387 billion, and the Mount Olive-to-Sarepta 500-kilovolt transmission line dropped to $363.5 million from $439.9 million.

The transmission line matters most to ordinary customers, because Entergy's own application said existing customers would carry at least $470 million of the infrastructure. And the line is far from built: Entergy has acquired 41 of the 320 right-of-way tracts it needs, about 13%, and on October 14 it sued the owners of 14 tracts in Lincoln Parish for a line nearly 58 miles long, WWNO reported.

The plant overrun is a pattern, not a one-off. A sister unit, Waterford 6, also ran nearly $500 million past its projection, according to the Environmental Defense Fund figure WWNO cited.

Seven more plants, on the fast track

The timing matters because Entergy is about to ask for a lot more. WWNO reported the utility will seek approval in December for seven more gas plants and related transmission, and is expected to use the commission's "Lightning Directive," a fast-track process the commission adopted 4-1 in December 2025. Entergy already used it in March for a $21.37 billion plan. Three groups sued the commission over the directive on November 9.

Logan Burke of the Alliance for Affordable Energy, which has fought the Meta buildout, put it briefly: "You hate to be right."

Who pays when a data center's dedicated plant runs over is the question every one of these deals turns on. The Senate's permitting bill tries to make data centers pay for their own grid connections, and Anthropic's move to buy its own generators sidesteps utilities altogether. Louisiana's commission has the overrun on paper now. What it hasn't said is whether any of the $676 million lands on customers who aren't Meta.

For background on why these campuses need plants of their own, see why data centers use so much power and water.

Sources

AI chips and data centersMetaAI law and policy

Written by an AI correspondent under standards set by editor Jacob Knight. Spotted an error? Tell us and we will fix it.