Lea County approves $130 billion in bonds for Google data center near Hobbs

Lea County, New Mexico, commissioners voted 4-1 on November 19 to approve a $130 billion industrial revenue bond for Project Rancho, Google's planned data center west of Hobbs, and unanimously rejected a six-month moratorium.

Kiln, covering chips, data centers and power
, 3 min read

$130Bindustrial revenue bond for Google's Project Rancho

What to know

  • Lea County commissioners approved the $130 billion industrial revenue bond 4-1 in Lovington on November 19; Commissioner Sims voted no.
  • The board voted unanimously against a proposed six-month data center moratorium backed by a residents' petition.
  • Google plans two 900,000-square-foot buildings on nearly 1,900 acres, powered by solar, with operations starting in 2029.

The biggest number in this deal is a ceiling, and the smallest one, what Lea County's schools will actually collect, hasn't been made public. Lea County's commissioners voted 4-1 on Thursday, November 19, in Lovington to approve a $130 billion industrial revenue bond for Project Rancho, Google's planned data center a few miles west of Hobbs, the Albuquerque Journal reported. In the same meeting they voted unanimously against a six-month data center moratorium that residents had petitioned for.

Commissioner Sims cast the only no vote, on the bond and on Local Economic Development Act funding. He and Commissioner Gary Eidson both conceded the process felt rushed, and Sims suggested putting the vote off a month, according to the Journal.

What the county actually signed

An industrial revenue bond in New Mexico is not a loan the county takes on. The county holds title to the project property and leases it to the developer, which pays negotiated payments in lieu of taxes (PILOT) instead of ordinary property tax, under a community benefits agreement. KOB 4 reported those payments would go to local governments, schools and hospital districts. The Journal names Google and Mosaic Ventures LLC as the parties, and the county's attorney, Peter Franklin, said some terms were still in flux and could be delegated to the county manager or chairman. One resident told the meeting the preliminary agreement ran about 800 pages.

So the $130 billion is a ceiling on the investment the deal covers, not money changing hands Thursday. Spread over the site, it works out to about $69 million per acre ($130 billion over roughly 1,890 acres). For a yardstick inside the same state, Project Jupiter in Doña Ana County won $165 billion in bonds for 1,400 acres, the Santa Fe New Mexican reported. Two New Mexico counties have now approved nearly $300 billion in data center bonds between them.

The building and the water

Google plans two 900,000-square-foot buildings with closed-loop cooling, powered by a large solar array. At town halls earlier this month Google described that array as a 2-gigawatt solar field about three miles away, to be built by Excelsior Energy, according to the New Mexican. KOB 4 reported construction starts in 2027 and operations in 2029. Google projects more than 1,000 construction jobs at peak and over 100 permanent ones.

Water is where the figures get slippery. At Thursday's meeting Google's Chris Adams said construction would use 2.8 acre-feet a day, or 912,384 gallons, drawn from effluent or imported water, the Journal reported. Operations would use up to 28 acre-feet a year per building. For two buildings that's 56 acre-feet, or about 18.2 million gallons a year, around 50,000 gallons a day. At the November town halls Google had cited about 40,000 gallons a day and 14.6 million gallons a year, plus an initial cooling fill of up to 9.7 million gallons, per the New Mexican. The Journal noted Thursday's presentation gave neither the fill volume nor the site's power demand.

The construction figure is the one to watch: on those numbers, a single day of building uses about as much water as 18 days of running the finished campus. We explained why closed-loop systems cut the ongoing draw in our power and water explainer.

The petition that lost

Lovington resident Clayburn Griffin brought the moratorium petition, which the Journal said carried hundreds of local signatures. Griffin told KOB 4 that 96% of 800 signers in a neighbors' survey opposed the project. Former Hobbs Mayor Sam Cobb backed it as a way to widen the county's economic base, KOB 4 reported.

Lea County went the opposite way from Cameron County, Texas, which turned down a SpaceX data center tax break this week, and from the cities still fighting over limits, such as Minneapolis. What nobody has put on the record yet is the size of the PILOT schedule itself: how many dollars a year reach Lea County's schools, and for how long.

Sources

AI chips and data centersGoogleAI law and policy

Written by an AI correspondent under standards set by editor Jacob Knight. Spotted an error? Tell us and we will fix it.