Kentucky Power asks to build a $2.8 billion gas plant for TeraWulf's data center
Kentucky Power has asked the Kentucky Public Service Commission to approve a roughly 760-megawatt gas plant in Louisa and a new substation to serve TeraWulf's 1-gigawatt Muskie Data Campus near Ashland, with TeraWulf covering financing costs and funding $100 million in winter bill credits.
Kiln, covering chips, data centers and power
, 3 min read
$2.81Bestimated cost of the Big Sandy gas plant
What to know
- Kentucky Power filed with the Kentucky PSC on Nov. 13 for a combined-cycle gas plant next to its Big Sandy unit in Louisa and a substation at EastPark Industrial Park.
- The plant would cost about $2.81 billion and come online in 2031, according to the Kentucky Lantern; the campus is meant to reach up to 1 GW by 2029.
- Decisions on the two certificates the utility needs could come as early as mid-2027, Kentucky Power said.
Kentucky Power has about 162,000 customers spread across 20 Eastern Kentucky counties. It now wants to build a power plant that would cost roughly $17,300 for each of them, and it wants that plant for one customer.
The utility, a subsidiary of American Electric Power, filed with the Kentucky Public Service Commission on Nov. 13 to build a combined-cycle natural gas plant next to its Big Sandy unit in Louisa, plus a new transmission substation at the EastPark Industrial Park near Ashland. The load behind it is TeraWulf's Muskie Data Campus, which the company's release says will grow in phases to as much as 1 gigawatt of contracted demand by 2029. The Kentucky Lantern, which read the filing, puts the plant at $2.81 billion and in service in 2031. The utility's release leaves the price out.
The sum is simple: $2.81 billion over 162,000 customers is about $17,300 apiece. Kentucky Power's answer is that TeraWulf, not those customers, pays the estimated financing costs, and an AEP vice president wrote in testimony that current ratepayers would see no rate increase, according to the Lantern.
What residents get
The release promises more than $500 million in fixed-cost rate offsets over the life of the contract and $100 million in winter bill credits for residential customers, starting in 2029 and running for the first 10 years. That's $10 million a year. The Lantern estimates the credits at about $26 a month per ratepayer in the winter months.
Those credits matter in this territory. Kentucky Power customers are already paying for part of a $191 million cooling tower at the Mitchell coal plant in West Virginia, a project the PSC's chair called "unpopular," WEKU reported in August. The commission is also auditing the utility's management. In that case the attorney general argued TeraWulf's load could help spread those costs, which is the same pitch the utility is making now on a far larger scale.
The gap years
The dates in the filing don't line up on their own. TeraWulf told investors in May that the first 500 megawatts would start ramping in the second half of 2028, with another 500 megawatts targeted for the second half of 2030, LEX 18 reported. The gas plant arrives in 2031. Until then, the Lantern reports, Kentucky Power would buy power generated elsewhere to serve the campus. Nobody has said in public how much that bridge power costs or who carries the price risk if the market is tight when it's needed.
The plant is also smaller than the load. The release gives 760 megawatts; the Lantern describes it as up to 769. Either way it covers about three-quarters of a gigawatt campus, and TeraWulf has said it may double the site. Kentucky Power is already building a 345-kilovolt substation tied to its 765-kilovolt network for the project, per LEX 18.
A site with a history
EastPark is where Braidy Industries planned an aluminum mill that never came, and the state clawed back a $15 million investment. WEKU counted two earlier aluminum proposals in Kentucky Power territory that fell through. TeraWulf's other Kentucky campus, at an idle smelter in Hancock County, is further along: the PSC approved its power contract in August, and Anthropic is the tenant.
The pattern is familiar from this month's filings. Ohio regulators approved two off-grid gas plants for data centers this week, as we reported, and Entergy's gas plant for Meta in Louisiana is now 63% over its first estimate. That overrun is the risk Kentucky's commission will have to price. A data center tenant covering financing on a 2031 plant is only as good as the contract terms if construction runs long or the campus never reaches a gigawatt. For why a single campus needs a power plant at all, see our explainer on data center power and water.
The generation plant and the transmission work each need their own certificate of public convenience and necessity. Kentucky Power says decisions could come as early as mid-2027, which would leave about four years to build a plant due in 2031, for a campus meant to start ramping in 2028.
Sources
- Kentucky Power Files Plans to Deliver Customer Savings and Advance Kentucky's Economic Future, American Electric Power via PR Newswire, November 13, 2026
- Kentucky Power asks state to build a $2.8 billion gas-fired power plant for big data center, Kentucky Lantern / States Newsroom, November 18, 2026
- TeraWulf acquires 1+ GW Eastern Kentucky HPC campus to expand AI infrastructure, LEX 18, May 27, 2026
- Data center could help lower cost of Kentucky Power cooling tower project, AG says, WEKU, August 24, 2026