Stafford County planners vote 4-3 to reject 1,400-acre data center campus
Stafford County, Virginia's planning commission recommended denial of all 11 applications for Peterson Companies' 37-building data center campus along Kings Highway after an 11-hour hearing. The Board of Supervisors has the final say.
Kiln, covering chips, data centers and power
, 2 min read
4-3Vote on each of 11 applications, recommending denial
What to know
- The Stafford County Planning Commission voted 4-3 on each of 11 rezoning, comprehensive plan and permit applications early Thursday, Nov. 19, recommending denial.
- The four-site project would rezone about 1,400 acres from agricultural to heavy industrial use for 37 data center buildings and 14 electrical substations, according to FOX 5.
- County staff put tax revenue at a peak near $218 million, leveling at about $193 million at full build-out; the Board of Supervisors has not scheduled its hearing.
A 37-building data center campus in Stafford County, Virginia, lost its first public vote. After an 11-hour meeting that ran from Wednesday night into early Thursday, Nov. 19, the Stafford County Planning Commission voted 4-3 on each of 11 applications to recommend that the Board of Supervisors deny them, according to FOX 5 DC and Potomac Local News.
The applications, from developer Peterson Companies, cover rezonings, comprehensive plan compliance reviews and conditional use permits for four sites along the Route 3 (Kings Highway) corridor. WJLA has reported the project under the name Kings Corridor Technology Campus.
How big it is
The plan would rezone about 1,400 acres from agricultural to heavy industrial use for 37 data center buildings and 14 electrical substations, FOX 5 reported. That is about 2.2 square miles (1,400 acres divided by 640 acres per square mile). Potomac Local put the buildings at about 9 million square feet after the developer cut 2 million square feet from the plan. Most of the land is in the George Washington District and largely outside the county's urban services area.
Neither report gave a megawatt figure for the campus, but 14 substations points to a very large power draw.
The money on each side
County staff, who had recommended denial ahead of the hearing according to WJLA, estimated that tax revenue from the reduced plan would peak near $218 million and level off at about $193 million at full build-out, Potomac Local reported. The developers told FOX 5 the four projects together could generate more than $268 million in revenue by 2036 and nearly 1,200 jobs.
Peterson Companies offered berms, tree preservation, stormwater controls, stream restoration and partnerships with Virginia State University and the University of Virginia. It said the campus would not use drinking water for cooling and would instead take reclaimed "purple pipe" water from a nearby treatment plant, according to Potomac Local.
The vote
More than 100 people signed up to speak, FOX 5 reported. Opponents raised farmland, the regional water supply, the Rappahannock River and historic areas near Ferry Farm, George Washington's boyhood home. Commissioner Kelsey V. Caudill of the George Washington District moved to deny the first application. "I can't in good conscience approve this," she said, according to Potomac Local. Commissioners Carlos Bratton, Maureen L. Siegmund and Marcus T. Oats voted in favor, citing section 3.11 of the county's Comprehensive Plan.
The recommendation is advisory. The Board of Supervisors makes the decision and has not scheduled a hearing.
Part of a wider pullback
Stafford's vote is the latest in a run of local governments slowing data center growth. Loudoun County, in the Northern Virginia market that holds the world's largest concentration of data centers, paused new legislative data center applications this month (Loudoun's pause), and Salt Lake City and Minneapolis have taken their own steps (Salt Lake City, Minneapolis).
Why it matters
Stafford's supervisors have already approved one data center project, Accokeek Creek, according to WJLA. A planning commission split this narrowly shows how evenly Stafford is weighing tax revenue that could approach $200 million a year against farmland, water and a campus with 14 substations. The supervisors' vote will decide it. For background, see our explainer on why data centers use so much power and water.
Sources
- Stafford Planning Commission recommends denial of 11 data center applications in 4-3 votes, Potomac Local News, November 19, 2026
- Stafford County Planning Commission recommends rejecting massive data center proposal, FOX 5 DC, November 19, 2026
- Stafford County postpones data center project hearing after county staff urged denial, WJLA 7News, October 13, 2026
AI chips and data centersAI law and policy
Written by an AI correspondent under standards set by editor Jacob Knight. Spotted an error? Tell us and we will fix it.