University of Michigan regents approve $785 million Los Alamos computing center over township opposition

The University of Michigan Board of Regents voted 7-1 on November 19 to proceed with a 100-megawatt high-performance computing center on Textile Road in Ypsilanti Township, where elected officials have formally opposed it.

Kiln, covering chips, data centers and power
, 3 min read

$785MCap on the center's two phases

What to know

  • Regents voted 7-1 on November 19 to authorize bids and contracts; Regent Paul Brown was the only no vote.
  • Phase one is estimated at $450 million for 150,000 square feet; both phases are capped at $785 million and 300,000 square feet.
  • As a state university, Michigan does not need Ypsilanti Township's zoning approval, and the township has passed resolutions opposing the project.

The University of Michigan will build its computing center in Ypsilanti Township whether the township wants it or not. On Thursday, November 19, the Board of Regents voted 7-1 to let the university seek bids and award contracts for the project, Planet Detroit reported. Regent Paul Brown cast the only no vote.

What was approved

The building goes on Textile Road in Ypsilanti Township, on a site Planet Detroit describes as sitting on the Huron River. According to a memo from chief financial officer Robert Hewlett cited by Planet Detroit, phase one is estimated at $450 million for 150,000 gross square feet. Phases one and two together are capped at $785 million and 300,000 gross square feet. WJR reported a 2031 target for completing the first phase.

The power figure is 100 megawatts, per Planet Detroit. For a yardstick, that is about a tenth of the 1,000 megawatts San Francisco's planners say the whole city's transmission lines can carry, the limit behind its data center moratorium. Run the cost arithmetic and phase one works out to about $3,000 per square foot, and the full cap to about $2,600, which is roughly $7.85 million per megawatt if all 100 megawatts arrive with phase two. That is a building packed with computing gear, not a warehouse.

Phase one is paid for with a State of Michigan grant and university bonds, Planet Detroit reported, with the debt serviced from rental payments and general fund money. The state's Michigan Strategic Fund and the Michigan Economic Development Corp. granted $100 million in 2024.

The township said no

Ypsilanti Township's elected officials oppose the center, citing noise, emissions from backup generators and risk to the Huron River, Planet Detroit reported. The township board, trustees and other local bodies have passed formal opposition resolutions and a utilities moratorium, The Eastern Echo reported, and Supervisor Brenda Stumbo had asked the university to pause. WJR reported that township leaders also raised concerns about the project's national-security and nuclear research ties.

None of that can stop it. As a state university, Michigan does not need local zoning approval, Planet Detroit noted. The regents paired the vote with a community partnership resolution and a pledge of $5 million over five years for Ypsilanti-area projects, covering education, parks, infrastructure and public safety. Stumbo told the Echo the resolution does not represent a true partnership.

About 150 protesters gathered outside the Alexander Ruthven Building in Ann Arbor before the meeting, the Echo reported. A student spoke against the project during public comment and asked for a delay; a representative of IBEW Local 252 spoke for it, citing construction jobs. Brown, explaining his vote, said the university could find a community that would welcome the project. Outgoing president Domenico Grasso said in a statement that the center would have no negative impact on the Huron River, according to Planet Detroit. The meeting was his last as president.

The university calls it a high-performance computing center. Opponents call it a data center. On the grid the label matters less than the load, and 100 megawatts is 100 megawatts either way.

Why it matters

Most local fights over data centers turn on a zoning vote, which is why towns from Loudoun County to Rochester, Minnesota have reached for pauses. Ypsilanti Township has passed every resolution it can, and a state university can still build over it. The open questions now are physical ones, and the township has little say over them: how the site gets 100 megawatts, how it is cooled, and what that means for the river next door. For why those two numbers dominate every project like this, see our explainer on why data centers use so much power and water.