Only about a fifth of utilities' reported data center demand is under contract, Latitude finds
Research firm Latitude Intelligence counts about 120 GW of signed data center load against 537 GW that US utilities report in their pipelines, a gap that matters for who pays for new power plants.
Kiln, covering chips, data centers and power
, 3 min read
22%share of reported data center load with signed contracts
What to know
- Latitude Intelligence counts about 120 GW of signed data center load across 53 US utility service territories, against 537 GW reported, according to Tech Times.
- About 22 GW of data center load is operating today in those territories.
- Georgia Power reports 80.1 GW of data center load, of which 12.8 GW is signed, by Latitude's count.
US utilities report far more data center demand than customers have actually signed up to buy. A count by Latitude Intelligence, the research service Latitude Media launched this month, finds about 120 gigawatts of data center load under signed agreements across 53 US utility service territories, against 537 GW that those utilities report in their pipelines. That is about 22%, according to Tech Times, which reported the figures on November 16. Latitude published the data on Friday, November 13.
Latitude's own launch material, published through MarketScale, puts the signed figure at about 123 GW out of "more than 500 GW." This story uses the Tech Times figures, which give an exact total; Latitude's original report was not available to read.
How Latitude counts
Utilities count data center demand in different ways. Some report every inquiry from a developer; others report only executed contracts. Latitude applies one rule to all of them: load counts as signed only when the customer has an executed agreement to take electric service. The rest of the reported total mixes planning forecasts, letters of interest and announcements.
For scale, about 22 GW of data center load is running today in the same territories, according to Tech Times. The signed load alone is about five and a half times that.
Where the gap is widest
Georgia Power, which serves the Atlanta area and the site of OpenAI's planned Project Camellia campus, reports 80.1 GW of data center load. Latitude counts 12.8 GW of it as signed.
Some utilities have signed far more than they serve today. Signed data center load at AEP Ohio equals 235% of that utility's peak demand, at NIPSCO in northern Indiana 169%, and at PPL in Pennsylvania 145%, according to Latitude's figures. PPL, for example, agreed this month to have a venture it co-owns build about 2 GW of generation for a QTS campus in Luzerne County.
Tech Times also cites a Jefferies analysis that sorted 187 GW of commitments disclosed by regulated utilities into tiers; only 69 GW sat in the strictest tier, formal electric service agreements. And it cites a Utility Dive report that PPL Electric, FirstEnergy and AES Ohio together cut their near-term large-load forecasts by 6.5 GW.
Utilities are still buying power plants
The count lands while utilities seek bids for about 37 GW of new generation, part of which ratepayers may end up paying for, according to Tech Times. Dominion Energy is seeking up to 7.3 GW of dispatchable generation, AEP has 4 GW of solicitations open, and Georgia Power is pursuing 2 to 6 GW more.
Equipment orders placed for projects that never arrive can be expensive. SoftBank last week wrote off $3.7 billion of prepaid US data center power equipment.
Why it matters
Utilities plan power plants and set rates based on the demand they expect. If most of the data center load in their pipelines is not under contract, the 37 GW of new generation they are seeking could be sized for customers who never arrive, and part of that cost may fall on ratepayers. It also gives cities weighing new campuses, such as Boise and Minneapolis, a firmer sense of how much proposed demand is real. For how much power these buildings use, see our explainer on why data centers need so much power and water.
Sources
- Latitude Finds Data Center Power Contracts Cover 22% of Reported Load as Utilities Seek Power Plants, Tech Times, November 16, 2026
- Latitude Intelligence finds only 123 GW of utilities' data center demand is under contract, MarketScale, November 16, 2026
AI chips and data centersAI law and policy
Written by an AI correspondent under standards set by editor Jacob Knight. Spotted an error? Tell us and we will fix it.