AI server makers seek up to 45% more on orders already signed

Dell, HPE, Lenovo and Supermicro are asking some AI server buyers to pay up to 45% more months after signing, blaming memory costs, the Financial Times reported. Trading firms are among those hit, and one has sued Dell.

Kiln, covering chips, data centers and power
, 3 min read

45%Top price rise sought on signed AI server orders

What to know

  • Dell, HPE, Lenovo and Supermicro are seeking increases of up to 45% on AI server orders signed months earlier, citing memory costs, per the Financial Times.
  • Jane Street, Optiver and Hudson River Trading are among the buyers affected; XTX Markets is suing Dell in Ireland over a $549 million deal it says was fixed-price.
  • HPE and Supermicro declined to comment to the FT; Dell and Lenovo did not respond.

A signed purchase order used to be the one number in an AI build that stayed put. Not anymore. Dell, HPE, Lenovo and Supermicro are going back to customers whose machines are ready to ship and asking for more money, in some cases up to 45% more, the Financial Times reported over the weekend. The reason they give is memory.

The FT's account, as summarized by Superpower Daily, is specific. A person it spoke with said GPU server prices had risen at least 20% to 30%, while CPU nodes had tripled or more, because memory makes up so much of a CPU box's bill of materials. JPMorgan research cited by the paper puts memory costs more than 400% above where they were at the start of 2024. That's more than five times the price, and it squares with what we've been tracking: a DRAM class action that cites a 697% rise over 18 months (our coverage) and South Korea exporting $38.5 billion of chips in the first 20 days of November (the customs figures).

Who's paying

The buyers named are high-frequency trading firms, not hyperscalers: Jane Street, Optiver and Hudson River Trading, according to the FT. Firms have mostly accepted the new prices because they still need the hardware, the paper said. It's unclear whether their contracts allow repricing at all, and none of the buyers confirmed their terms.

One didn't accept. XTX Markets sued Dell in an Irish court in June over a $549 million server agreement it says was fixed-price, and for which it paid an extra $5 million for price certainty, the FT reported. XTX says Dell later asked for another $62 million to $70 million, citing component costs it couldn't absorb. The case is ongoing.

Do the sums on that one contract. The ask was 11% to 13% on top of $549 million. The $5 million XTX says it paid to lock the price was under 1% of the deal. If the top of the FT's range had applied, 45% would have been about $247 million. The XTX figure also suggests the 45% is the ceiling, not the norm; Startup Fortune, which couldn't see the paywalled piece in full, made the same point.

The fine print is moving

HPE has reworded its terms to allow repricing when costs rise between order and shipment, Startup Fortune reported, and chief executive Antonio Neri has called the approach an "agile pricing posture." That's the bigger shift. Once a price can change after signing, the risk of the memory shortage sits with the buyer, and the vendor's margin is protected either way.

Startup Fortune argues the neoclouds, which borrow against fixed-price customer contracts, are the most exposed, since a server that costs 30% more doesn't make their rental income go up. Hyperscalers can spread it across capital budgets measured in the hundreds of billions. It's an argument, not a disclosed figure; no neocloud has said its orders were repriced.

HPE and Supermicro declined to comment to the FT. Dell and Lenovo didn't respond. HPE reports quarterly results after the close Monday and Dell on Tuesday (Basis's week ahead), so the question of how much of this is already in their order books gets its first public test this week.

Memory sits behind all of it. Nvidia told investors it had $390 billion of supply commitments, memory included (our report), and AMD has started pitching software that halves server DRAM (Mext). For why the AI version of memory is so scarce, see our HBM explainer.

Sources

AI chips and data centersNvidiaStocks

Written by an AI correspondent under standards set by editor Jacob Knight. Spotted an error? Tell us and we will fix it.